RA bill format for contractors: what goes into a running account bill
A running account bill (RA bill) is how a contractor gets paid while the work is still going on. Instead of waiting for the end of the project, the contractor bills every month (or at agreed stages) for the work done so far, and the consultant or client certifies it.
Most payment delays come from bills that are hard to check: quantities that don't match the measurement book, a previous total that doesn't match what was certified last time, or deductions nobody can trace. A clean format avoids all three.
The five parts of an RA bill
- Header: project name, work order or contract number, contractor and client names and GSTINs, bill number (RA-1, RA-2 …), bill date and the period the bill covers.
- Abstract (the BOQ table): every BOQ item worked on, with previous, this bill and cumulative quantities and amounts.
- Extra and variation items: work outside the BOQ, each with its approval reference. Keep these separate from BOQ items.
- Deductions and taxes: retention, advance recoveries, TDS, labour cess, GST and any other recoveries, each shown on its own line.
- Summary: value of work to date, less previous bills, value of this bill, deductions and the net amount payable.
Attach the measurement sheets, site photos and any test reports. A checker should be able to trace every quantity in the bill back to a measurement.
The columns of the BOQ table
The table is the heart of the bill. Use the same item numbers, descriptions, units and rates as the BOQ in the contract, and show three quantities for every item:
- Previous: the cumulative quantity certified up to the last bill (not what you claimed last time).
- This bill: the quantity done in this period.
- Cumulative: previous plus this bill. This should never exceed the BOQ quantity without an approved variation.
A worked example
RA-3 for a small block of work, with three BOQ items:
| Item | Description | Unit | BOQ qty | Rate (₹) | Previous qty | This bill qty | Cumulative qty | This bill (₹) | Cumulative (₹) |
|---|---|---|---|---|---|---|---|---|---|
| 1 | PCC M15 in foundations | cum | 120 | 5,800 | 60 | 30 | 90 | 1,74,000 | 5,22,000 |
| 2 | Brick masonry 230 mm in CM 1:6 | cum | 300 | 6,500 | 100 | 50 | 150 | 3,25,000 | 9,75,000 |
| 3 | 12 mm internal plaster in CM 1:4 | sqm | 2,000 | 420 | 0 | 800 | 800 | 3,36,000 | 3,36,000 |
| Value of work | 8,35,000 | 18,33,000 | |||||||
Check the arithmetic the way a consultant will: previous work was 3,48,000 + 6,50,000 + 0 = 9,98,000, and 9,98,000 + 8,35,000 = 18,33,000, which matches the cumulative column.
Summary and deductions for this bill
| Value of work in this bill | 8,35,000 |
| Add: GST at 18% | 1,50,300 |
| Gross amount of this bill | 9,85,300 |
| Less: retention at 5% of work value | 41,750 |
| Less: TDS at 2% of work value | 16,700 |
| Less: labour welfare cess at 1% | 8,350 |
| Less: mobilisation advance recovery | 50,000 |
| Total deductions | 1,16,800 |
| Net amount payable | 8,68,500 |
Common mistakes that delay payment
- Previous quantities taken from your own last claim instead of the last certified bill. The consultant will reject the bill and ask you to redo it.
- Cumulative quantity above the BOQ with no approved variation attached.
- Extra items mixed into BOQ items, so nobody can tell what was approved.
- Rounded or shortened amounts (“8.35 L”). Always write the exact rupee amount.
- Missing measurement sheets for the quantities claimed.
A checklist before you send the bill
- Bill number and period follow on from the last bill
- Previous quantities match the last certified bill
- No cumulative quantity is above the BOQ without approval
- Every deduction is on its own line, with its rate
- Measurement sheets and photos are attached
How ZEOEZ ERP does it
In ZEOEZ ERP the contractor picks the BOQ items and enters this period's quantities. Previous and cumulative quantities come from the certified bills automatically, deductions follow the contract, and the bill prints in a clean format. The consultant certifies it in the same place, so both sides always see the same numbers.
Raise and certify bills in ZEOEZ ERP
Previous, this bill and cumulative quantities worked out for you. Free until 31 March 2027.