Blog

How to certify a contractor's running bill: a step-by-step guide

zeoez · 19 November 2026

When a contractor sends a running account (RA) bill, the consultant or project management consultant (PMC) checks it and certifies how much the client should pay. The certificate protects the client from paying for work that wasn't done, and protects the contractor by putting an agreed number on record.

Here are the checks to make, in the order that saves the most time.

1. Check that the bill is complete

Before checking any numbers, confirm the bill has what you need: bill number and period, the BOQ abstract with previous, this bill and cumulative columns, measurement sheets, photos, and test reports where the contract asks for them. Send an incomplete bill back straight away with a list of what's missing.

2. Check the previous figures

The “previous” quantities and amounts must match what you certified last time, not what the contractor claimed. This is the most common error, and every later check depends on it.

3. Check the quantities

  • Compare the quantities with the measurement book or joint measurement records.
  • Check on site where it matters: high-value items, hidden work (foundations, reinforcement, waterproofing) and anything that looks high.
  • The cumulative quantity should not cross the BOQ quantity unless a variation has been approved.

4. Check rates and items

  • Every rate must match the contract BOQ.
  • Extra items need an approved rate and an approval reference. Keep them separate from BOQ items.
  • Watch for items billed under the wrong BOQ number to use a better rate.

5. Check deductions and taxes

Retention, mobilisation and material advance recoveries, TDS, labour cess and other recoveries (water, power, material issued by the client, debit notes) must follow the contract. Check that each advance is being recovered at the agreed rate and that GST is worked on the right base.

6. Record what you hold back, with a reason

You will often certify less than the claim. Write down every reduction on its own line:

ItemClaimed (₹)Certified (₹)Reason
2 · Brick masonry3,25,0002,92,5005 cum not yet measured jointly; to be taken in next bill
3 · Internal plaster3,36,0003,36,000Agreed
Extra 1 · Chicken mesh at joints18,4000No approved variation yet

Clear reasons turn a dispute into a to-do list: the contractor knows exactly what to fix, and the held amount comes back in the next bill once it is sorted.

7. Issue the certificate

The certificate should show, in exact rupees:

  • the amount claimed and the amount certified;
  • value of work certified to date, less previous certificates;
  • each deduction and the net amount payable;
  • the reasons for any amount held back;
  • your name, date and signature.

Send it to the client for payment and to the contractor for their records, and keep track of when it is paid. A certified amount that sits unpaid for months is a problem for everyone on the project.

Keep one version of the truth. Most certification arguments come from the contractor, consultant and client each keeping their own spreadsheet. When all three work from the same bill and the same certified history, the numbers can't drift apart.

How ZEOEZ ERP helps

In ZEOEZ ERP the contractor raises the bill and the consultant certifies it in the same place. Previous figures always come from the last certified bill, every change is recorded, reasons for held amounts stay with the bill, and the client sees what has been certified and what is still unpaid.

Certify bills in ZEOEZ ERP

Previous, this bill and cumulative quantities worked out for you. Free until 31 March 2027.